China business trip report — MB1000 P32 setup for Helios NanoLab G3 UC (FEI), January 2017

Worksheet dated 2017.01.16 covering trip 17.01.11–17.01.14: MB1000_P32 setup for a Helios NanoLab G3 UC (FEI) with ACTIVE tuning summary, internal-program performance plots (Z/X/Y), and vibration-environment measurement plots (Z/X/Y). SEM imaging feedback after tool operation was agreed to be handled via NEMO.

FEI Teneo LoVac DVIA-MB1000 (MB1000 P33) China trip report — 2017.01.16

MB1000 P33 worksheet, target equipment FEI Teneo LoVac, business trip 17.01.11–17.01.14, operators Choi HyoungMun (代理) and Lim Jongwook (主任), written 2017.01.16. The centred title-banner raster (DOCX §2a `image1`, empty-heading paragraph) was not republished; the figure after the 타겟 장비 line (`image2`) is published as equipment context photography. MB1000 internal-program screenshots and vibration-environment octave-band traces follow paragraph-order §2a mapping (`image3`–`image8`). The VC-Class ACTIVE summary is conveyed by the verbatim table cells only — no separate VC-curve raster appears in this report.

Hankook Tire Technodome Hitachi SU8010 DVIA-MB1000 (P38) vibration environment measurement — 2016.12.28

MB1000 program project P38 handout documenting post-installation vibration environment measurement for a Hitachi SU8010-class SEM at Hankook Tire Technodome, Daejeon (report line: 1st floor research building). Measurement 2016-12-27; report authored 2016-12-28 by DAEIL SYSTEMS field engineers Kim Duhyun (Deputy Manager) and Lim Jongwook (Senior Engineer). VC-Class summary for the slab floor versus the DVIA tabletop, VC-Class Z/X/Y plots, and internal-program Z/X/Y transmissibility plots follow DOCX §2a embed-to-heading mapping; centred masthead raster image1 (title block garnish only) omits publication.

Saeron Technology MB1000 P37 setup result — in-house SEM vibration survey with DVIA-MB1000 (2016-12-22)

Survey report dated 22 December 2016 for MB1000 P37 supporting an in-house SEM at Saeron Technology in Uiwang, Gyeonggi-do (5F). Measurement was performed on 21 December under active DVIA-MB1000 control, comparing floor versus platform vibration before and after SEM operation, with VC-class plots and MB1000 internal-program transmissibility captured for vertical and horizontal axes. The decorative header graphic at the very start of the DOCX is not published.

Tongji University (Shanghai) ZEISS SIGMA 300VP DVIA-MB1000 (MB1000 P28) China business trip worksheet — 2016.11.21

Korean-format China business-trip worksheet for MB1000_P28: target ZEISS SIGMA 300VP SEM, setup and vibration-environment work at Shanghai Tongji University on 16–17 Nov 2016; report dated 2016-11-21 by Deputy Lim Jong-wook. The public page publishes the SEM installation photo after the target-equipment line (DOCX image2, §2a), MB1000 internal-program Z / X / Y captures (image3–5), vibration-environment Z / X / Y plots (image6–8), and ~1M× SEM image comparison PASSIVE vs ACTIVE (image9–10 TIFF→WebP). The approval block raster at the document start (Word image1) is omitted.

Guangzhou ENF Hitachi SEM SU8010 DVIA-MB1000 (MB1000 P35) vibration-environment report — 2016.11.11

Korean-format worksheet for MB1000 program line P35 with target microscope HITACHI SEM SU8010 following active isolator deployment at Guangzhou ENF; trip dated 2016-11-09 and report dated 2016-11-11. The VC-Class summary covers the laboratory floor slab and the isolator tabletop, followed by appended Z-, X-, and Y-axis VC environment plots and a supplementary measurement-program capture.