07-05-2024

LG Chem (Nanjing) ZEISS CrossBeam 550 DVIA-M1000 (231205R4) Installation Report

DVIA-M Series
Installation Report
LG Chem
Nanjing
ZEISS
CrossBeam 550
DVIA-M1000
231205R4

LG化学

(MB1000_ 231205R4 Set-up)

LabelValue
Target equipmentZeiss CrossBeam 550
Place of installation南京
RemarkGood Performance
END USERLG化学 (南京)

Operator: Chaewon Lee

Date of setup: 24.06.17

Date of reporting: 24.07.05

Date of business trip : 17.12.27~17.12.29

Overview

The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.

Measurement date: 2024.06.26 (Wednesday)

Operator: Byeonghun Cho from DAEIL SYSTEMS

Place of measurement: 南京

Equipment Model: Zeiss Crossbeam 550

5.

M1000 internal program performance measurement result

Vertical

Left to Right

Front to Back

Share this Case Study

Case Study Information

Category
Installation Report
SeriesDVIA-M Series
Date07-05-2024
Tags
DVIA-M Series
Installation Report
LG Chem
Nanjing
ZEISS
CrossBeam 550
DVIA-M1000
231205R4