Installation Report
DVIA-M Series
11-01-2023
Huawei Solaris GMH DVIA-M1000 Installation Report (230509R6-2)
DVIA-M Series
Installation Report
Huawei
Solaris GMH
DVIA-M1000
Shanghai
Contents
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date
2023.11.01 (Wednesday)
Operator
Operator: DAEIL SYSTEMS Hosang Yu
Place of measurement
Shanghai
Equipment Model
Solaris GMH
M1000 internal program performance measurement result
Z axis
X axis
Y axis
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date11-01-2023
Tags
DVIA-M Series
Installation Report
Huawei
Solaris GMH
DVIA-M1000
Shanghai
Related Case Studies

DVIA-M Series
Shanghai Jiao Tong University Hitachi SU8600 FE-SEM DVIA-M1000 (250320R3) Installation Report
04-13-2026Read more

DVIA-M Series
YIMO Shanghai Pumi PrMat STM DVIA-M1000 (241101R2) Installation Report — Huasheng Lianying Vibration Damping Platform
01-23-2026Read more

DVIA-M Series
Tongji University Raith Voyager MAX EBL DVIA-M1000 (250402R6) Installation Report
08-07-2025Read more