Skip to main content
Installation Report
DVIA-M Series
06-13-2023

HUAI HONG DA Sigma 300 DVIA-M1000 (230417R8) Installation Report

DVIA-M Series
Installation Report
HUAI HONG DA
DVIA-M1000
230417R8
Sigma 300
Changzhou

HUAI HONG DA

HUAI HONG DA

(M1000_ 230417R8 Set up)

Site checklist

Target equipmentSigma 300
Place of installationCHANGZHOU
RemarkGood Performance
END USERHUAI HONG DA

Operator and dates

Operator: Lee, Young Ha

Date of setup: 23.06.06

Date of reporting: 23.06.13

Date of business trip : 17.12.27~17.12.29

Overview

The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.

Measurement date: 2023.06.06 (Tuesday)

Operator: DAEIL SYSTEMS, Youngha Lee

Place of measurement: CHANGZHOU

Equipment Model: HUAI HONG DA

5.

MB1000 internal program performance measurement result

Z axis

X axis

Y axis

Share this Case Study

Case Study Information

Category
Installation Report
SeriesDVIA-M Series
Date06-13-2023
Tags
DVIA-M Series
Installation Report
HUAI HONG DA
DVIA-M1000
230417R8
Sigma 300
Changzhou