Installation Report
DVIA-M Series
01-10-2025
ZEISS Innovation Center ZEISS Sigma 360 VP DVIA-M1000 (220121R3) Internal Program Performance — 2025.01.10
DVIA-M Series
Installation Report
ZEISS
ZEISS Innovation Center
Sigma 360 VP
FE-SEM
Shanghai
DVIA-M1000
220121R3
Contents
(M1000_220121R3 Set up)
| Target equipment | ZEISS Sigma 360 VP |
|---|---|
| Place of installation | Shanghai |
| Remark | Good Performance |
| END USER | ZEISS Innovation Center |
| Operator: Chaewon Lee, Jonghwa Suh | Date of business trip : 17.12.27~17.12.29 |
| Date of setup: 25.01.10 | |
| Date of reporting: 25.01.13 |
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date
2025.01.10 (Friday)
Operator
Operator: DAEIL SYSTEMS Chaewon Lee, Jonghwa Suh
Place of measurement
Shanghai
End User
End User: ZEISS Innovation Center
Equipment Model
Manufacturer: ZEISS
Equipment: FE-SEM
Model: Sigma 360 VP
M1000 internal program performance measurement result
Vertical
Left to Right
Front to Back
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date01-10-2025
Tags
DVIA-M Series
Installation Report
ZEISS
ZEISS Innovation Center
Sigma 360 VP
FE-SEM
Shanghai
DVIA-M1000
220121R3
Related Case Studies

DVIA-M Series
ZEISS Innovation Center Sigma 360 VP DVIA-M1000 Installation Report (YIMO, Shanghai, 2025-07-03)
07-03-2025Read more

DVIA-M Series
ZEISS DEMO Laboratory Sigma 360 VP DVIA-M1000 Installation Report (Shanghai)
04-29-2025Read more

DVIA-M Series
Integrated Service Technology ZEISS Gemini 560 DVIA-M1000 (230927R4) Setup — Shanghai
12-19-2023Read more