The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2022.10.19 (Wednesday),
Operator: DAEIL SYSTEMS, Youngha Lee
Place of measurement: Shanghai
Equipment Model: TBD
M1000 internal program performance measurement result
Z axis
X axis
Y axis