Contents
(MB1000_ 230908R3-3 Set-up)
Site checklist
| Target equipment | Thermo Fisher Helios 5 UX |
|---|---|
| Place of installation | N/A |
| Remark | Good Performance |
| END USER | N/A |
Operator and dates
Operator: Byeonghun Cho
Date of setup: 24.06.20
Date of reporting: 24.06.20
Date of business trip : 17.12.27~17.12.29
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2024.06.17 (Monday)
Operator: Byeonghun Cho from DAEIL SYSTEMS
Place of measurement: N/A
Equipment Model: Thermo Fisher Helios 5 UX
5.
Vibration Spec
M1000 internal program performance measurement result
Vertical
Left to Right
Front to Back
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date06-20-2024
Tags
DVIA-M Series
Installation Report
Thermo Fisher Scientific
Helios 5 UX
DVIA-M1000
230908R3-3
Related Case Studies

DVIA-M Series
Peking University Shenzhen Graduate School Thermo Fisher Helios 5 CX FIB-SEM DVIA-M1000 (250613R3) Installation Report
11-11-2025Read more
DVIA-M Series
Chinese Academy of Sciences Institute of Semiconductors Thermo Fisher Helios 5 CX DVIA-M1000 (250619R4) Installation Report
09-01-2025Read more

DVIA-M Series
Hangzhou Thermo Fisher Helios 5 CX FIB-SEM DVIA-M1000 (250417R2) Installation Report
06-09-2025Read more