Installation Report
DVIA-M Series
07-24-2023
PXW TESCAN SOLARIS GMH DVIA-M1000 (230501R3-4) Installation Report
DVIA-M Series
Installation Report
PXW
DVIA-M1000
230501R3-4
TESCAN
SOLARIS GMH
Shenzhen
Contents
PXW
PXW
(M1000_ 230501R3-4 Set up)
Site checklist
| Target equipment | TESCAN SOLARIS GMH |
|---|---|
| Place of installation | Shenzhen |
| Remark | Good Performance |
| END USER | PXW |
Operator and dates
Operator: Lee, Young Ha
Date of setup: 23.07.21
Date of reporting: 23.07.24
Date of business trip : 17.12.27~17.12.29
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2023.07.21 (Friday)
Operator: DAEIL SYSTEMS, Youngha Lee
Place of measurement: Shenzhen
Equipment Model: TESCAN SOLARIS GMH
5.
M1000 internal program performance measurement result
Z axis
X axis
Y axis
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date07-24-2023
Tags
DVIA-M Series
Installation Report
PXW
DVIA-M1000
230501R3-4
TESCAN
SOLARIS GMH
Shenzhen