Installation Report
DVIA-M Series
04-07-2023
Helios G5 CX DVIA-M1000 Report (221107R1 — GRGT, Shanghai, 2023-04-07)
DVIA-M Series
Installation Report
DVIA-M1000
Helios G5 CX
GRGT
Shanghai
Contents
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2023.03.29 (Wednesday),
Operator: DAEIL SYSTEMS, Hosang Yu
Place of measurement: Shanghai
Equipment Model: Helios G5 CX
5. MB1000 internal program performance measurement result
Z axis
X axis
Y axis
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date04-07-2023
Tags
DVIA-M Series
Installation Report
DVIA-M1000
Helios G5 CX
GRGT
Shanghai
Related Case Studies

DVIA-M Series
GRGT Shanghai Thermo Fisher Helios G5 CX DVIA-M1000 Internal Program Measurement
08-07-2024Read more

DVIA-M Series
GRGT Helios G5 CX DualBeam DVIA-M1000 (230818R1-1) Installation Report
12-06-2023Read more

DVIA-M Series
Thermo Fisher Scientific Apreo 2S HiVac DVIA-M1000 Installation Report
11-09-2023Read more