Reporting organization
广电计量
M1000_ 230821R3-2 Set up
Report summary
| Target equipment | Thermo Fisher Helios G5 |
|---|---|
| Place of installation | Wuxi |
| Remark | Good Performance |
| END USER | 广电计量 |
| Operator: Lee, Chaewon Date of setup: 24.03.20 Date of reporting: 24.03.21 | Date of business trip : 17.12.27~17.12.29 |
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended. The center of gravity of the equipment above the product is not aligned, so a resonance peak occurs around 34Hz. Measurement date: 2024.03.20 (Wednesday) Operator: DAEIL SYSTEMS Chaewon Lee Place of measurement: 无锡 Equipment Model: Thermo Fisher Helios G5
M1000 internal program performance measurement result
Vertical
Left to Right
Front to Back
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date03-21-2024
Tags
DVIA-M Series
Installation Report
Thermo Fisher Scientific
Helios G5
DVIA-M1000
230821R3-2
Related Case Studies

DVIA-M Series
YIMO Shenzhen Weiguang Thermo Fisher Scientific Helios G5 FIB-SEM DVIA-M1000 (240415R3-3) Installation Report
11-28-2024Read more

DVIA-M Series
Peking University Shenzhen Graduate School Thermo Fisher Helios 5 CX FIB-SEM DVIA-M1000 (250613R3) Installation Report
11-11-2025Read more
DVIA-M Series
Chinese Academy of Sciences Institute of Semiconductors Thermo Fisher Helios 5 CX DVIA-M1000 (250619R4) Installation Report
09-01-2025Read more