Installation Report
DVIA-P Series
02-15-2023
Shenzhen Optiark EBPG5200 DVIA-P4000 (221212R1) Installation Report — GUANGDONG — 2023.02.15
DVIA-P Series
Installation Report
Shenzhen Optiark
EBPG5200
GUANGDONG
DVIA-P4000
221212R1
Contents
Shenzhen Optiark Semiconductor Technologies Co., Ltd.
(P4000_221212R1 Set up)
Equipment photo
Target equipment and site
| Target equipment | EBPG5200 |
|---|---|
| Place of installation | GUANGDONG |
| Remark | Good Performance |
| END USER | EBPG5200 |
Report details
| Operator: Yu, Ho sang<br>Date of setup: 23.02.15<br>Date of reporting: 23.02.21 | Date of business trip : 17.12.27~17.12.29 |
|---|
Overview
The DVIA-P4000 active vibration isolation platform is appropriately installed and functioning as intended. (prior to equipment installation).
Measurement date
2023.02.15 (Wedday)
Operator
Operator: DAEIL SYSTEMS, Hosang Yu
Place of measurement
GUANGDONG
Equipment Model
EBPG5200
MB1000 internal program performance measurement result
Z axis
X axis
Y axis
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-P Series
Date02-15-2023
Tags
DVIA-P Series
Installation Report
Shenzhen Optiark
EBPG5200
GUANGDONG
DVIA-P4000
221212R1
Related Case Studies

DVIA-P Series
YIMO Huahong FAB 9 ASML E-beam Wafer inspection system eScan460 DVIA-P4000 Installation Report
06-15-2026Read more

DVIA-P Series
Huahong ASML eScan460 DVIA-P4000 Installation Report
06-11-2026Read more
DVIA-P Series
Tier-1 Semiconductor Advantest E5610 DVIA-P4000 Installation Report
05-21-2026Read more