Skip to main content
Installation Report
DVIA-M Series
11-21-2022

Chinese Academy of Social Sciences Institute of Archaeology Thermo Scientific Quattro S DVIA-M1000 (210719R5) Installation Report — Beijing

DVIA-M Series
Installation Report
Chinese Academy of Social Sciences
Institute of Archaeology
Thermo Scientific
Quattro S
SEM
DVIA-M1000
210719R5
Beijing

THE INSTITUTE OF ARCHAEOLOGY CASS

THE INSTITUTE OF ARCHAEOLOGY CASS

(M1000_ 210719R5 Set up)

Site checklist

Target equipmentQuattro S
Place of installationBEIJING
RemarkGood Performance
END USERTHE INSTITUTE OF ARCHAEOLOGY CASS

Operator and dates

Operator: Lee, Young Ha Date of setup: 22.11.17 Date of reporting: 22.11.21Date of business trip : 17.12.27~17.12.29

Overview

The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended. Measurement date: 2022.11.17 (Thursday), Operator: DAEIL SYSTEMS, Youngha Lee Place of measurement: BEIJING Equipment Model: Quattro S

MB1000 internal program performance measurement result

Z axis

X axis

Y axis

Share this Case Study

Case Study Information

Category
Installation Report
SeriesDVIA-M Series
Date11-21-2022
Tags
DVIA-M Series
Installation Report
Chinese Academy of Social Sciences
Institute of Archaeology
Thermo Scientific
Quattro S
SEM
DVIA-M1000
210719R5
Beijing