Skip to main content
Installation Report
DVIA-M Series
07-27-2023

Thermo Fisher Scios 2 DVIA-M1000 (210322R1) Installation Report — CETC 13 institute (Shijiazhuang)

DVIA-M Series
Installation Report
CETC
Shijiazhuang
Thermo Fisher
SCIOS
DVIA-M1000
210322R1

Customer and setup title

CETC 13 institute

(M1000_ 210322R1 Set up)

Target equipment and site

Target equipmentThermofisher Scios2
Place of installationShijiazhuang
RemarkGood Performance
END USERCETC 13 institute

Report details

Operator: Lee, Young Ha<br>Date of setup: 23.07.27<br>Date of reporting: 23.07.27Date of business trip : 17.12.27~17.12.29
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2023.07.27 (Thursday)
Operator: DAEIL SYSTEMS, Youngha Lee
Place of measurement: Shijiazhuang
Equipment Model: Thermofisher Scios2
5.

M1000 internal program performance measurement result

M1000 internal program — Z axis

M1000 internal program — X axis

M1000 internal program — Y axis

Share this Case Study

Case Study Information

Category
Installation Report
SeriesDVIA-M Series
Date07-27-2023
Tags
DVIA-M Series
Installation Report
CETC
Shijiazhuang
Thermo Fisher
SCIOS
DVIA-M1000
210322R1