Contents
Hainan University
海南大学
(M1000_ 231228R1 Set up)
Site checklist
| Target equipment | Thermo Fisher Helios PFIB |
|---|---|
| Place of installation | 海南 |
| Remark | Good Performance |
| END USER | 海南大学 |
Operator and dates
Operator: Lee, Youngha
Date of setup: 24.01.30
Date of reporting: 24.02.01
Date of business trip : 17.12.27~17.12.29
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2024.01.30 (Tuesday)
Operator: DAEIL SYSTEMS Youngha Lee
Place of measurement: 海南
Equipment Model: Thermo Fisher Quattro S
5.
M1000 internal program performance measurement result
Z axis
X axis
Y axis
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date01-30-2024
Tags
DVIA-M Series
Installation Report
Hainan University
Thermo Fisher
Helios PFIB
Quattro S
DVIA-M1000
231228R1
海南
Related Case Studies

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231004R3-1) Installation Report — 2024.05.09
05-09-2024Read more

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231004R3-1) Installation Report
04-15-2024Read more

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231113R4-1) Installation Report — 2024.04.15
04-15-2024Read more