Site checklist
| Target equipment | ZEISS Crossbeam350 |
|---|---|
| Place of installation | N/A |
| Remark | Good Performance |
| END USER | N/A |
Operator and dates
Operator: Chaewon Lee
Date of setup: 24.11.08
Date of reporting: 24.11.11
Date of business trip : 17.12.27~17.12.29
Overview
Overview
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2024.11.08(Friday)
Operator: Chaewon Lee from DAEIL SYSTEMS
Place of measurement: N/A
Equipment Model: N/A
Manufacturer: ZEISS
Equipment: FIB-SEM
Model: Crossbeam350
5.
M1000 internal program performance measurement result
Vertical
Left to Right
Front to Back
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date11-08-2024
Tags
DVIA-M Series
Installation Report
ZEISS
Crossbeam 350
FIB-SEM
DVIA-M1000
231219R4
Related Case Studies

DVIA-M Series
Shenghe Jingwei ZEISS Crossbeam 350 FIB-SEM DVIA-M1000 (240409R2) Installation Report
05-11-2026Read more

DVIA-M Series
ZEISS FIB-SEM Crossbeam 350 DVIA-M1000 (250108R5) Installation Report
06-09-2025Read more

DVIA-M Series
ZEISS FIB-SEM Crossbeam 350 DVIA-M1000 (250102R2-3) Installation Report
03-25-2025Read more