Installation Report
DVIA-M Series
03-25-2024
Hainan University Thermo Fisher Spectra 300 DVIA-M-JT1 (230918R3) Internal Program Performance — 2024.03.25
DVIA-M Series
Installation Report
Hainan University
Thermo Fisher
Spectra 300
DVIA-M-JT1
230918R3
海南
Contents
BCPCA
(M-JT1_ 230918R3 Set up)
Equipment picture
Hainan University
海南大学
| Target equipment | Thermo Fisher Spectra 300 |
|---|---|
| Place of installation | 海南 |
| Remark | Good Performance |
| END USER | 海南大学 |
| Operator: Lee, Chaewon | Date of business trip : 17.12.27~17.12.29 |
| Date of setup: 24.03.25 | |
| Date of reporting: 24.07.05 |
Overview
The DVIA-M-JT1 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date
2024.03.25 (Monday)
Operator
Operator: DAEIL SYSTEMS Chaewon Lee
Place of measurement
Beijing
Equipment Model
JEOL JEM-F200
5.
M-JT1 internal program performance measurement result
Vertical
Left to Right
Front to Back
Share this Case Study
Case Study Information
Category
Installation Report
SeriesDVIA-M Series
Date03-25-2024
Tags
DVIA-M Series
Installation Report
Hainan University
Thermo Fisher
Spectra 300
DVIA-M-JT1
230918R3
海南
Related Case Studies

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231004R3-1) Installation Report — 2024.05.09
05-09-2024Read more

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231004R3-1) Installation Report
04-15-2024Read more

DVIA-M Series
Hainan University Thermo Fisher Spectra 300 DVIA-MB3000 (231113R4-1) Installation Report — 2024.04.15
04-15-2024Read more