개요

CNITECH

(M1000_ 230908R2-2 Set up)

The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.

Measurement date: 2024.01.11 (Thursday)

Operator: DAEIL SYSTEMS Jongwon Park

Place of measurement: Ningbo

Equipment Model: ZEISS FE-SEM Sigma 300

Target equipment: Sigma 300

Place of installation: Ningbo

Remark: Good Performance

END USER: CNITECH

Operator: Park, Jongwon

Date of setup: 24.01.11

Date of reporting: 24.01.16

Date of business trip: 17.12.27~17.12.29

M1000 내부 프로그램 성능 측정 결과

Z축

X축

Y축

이 케이스 스터디 공유하기

케이스 스터디 정보

카테고리
설치 보고서
시리즈DVIA-M Series
작성일01-16-2024
태그
DVIA-M Series
Installation Report
CNITECH
ZEISS
FE-SEM
Sigma 300
DVIA-M1000
230908R2-2
Ningbo