현장 확인 항목

Target equipmentSTM
Place of installationN/A
RemarkGood Performance
END USERN/A

운영자 및 일정

Operator: Byeonghun Cho

Date of setup: 24.07.01

Date of reporting: 24.07.06

Date of business trip : 17.12.27~17.12.29

개요

The DVIA-MO1000 active vibration isolation platform is appropriately installed and functioning as intended.

Measurement date: 2024.07.01(Monday)

Operator: Byeonghun Cho from DAEIL SYSTEMS

Place of measurement: N / A

Equipment Model:

Manufacturer: Custom Equipment

Equipment: STM

5.

MB1000 내부 프로그램 성능 측정 결과

Vertical

Left to Right

Front to Back

이 케이스 스터디 공유하기