설치 보고서
DVIA-M Series
11-24-2023
China University Of Geosciences (Wuhan) Apreo DVIA-M1000 (230224R2) Installation Report
DVIA-M Series
Installation Report
China University Of Geosciences
Wuhan
Apreo
DVIA-M1000
230224R2
Contents
China University Of Geosciences,wuhan
China University Of Geosciences,wuhan
(M1000_ 230224R2 Set up)
현장 확인 항목
| Target equipment | Apreo |
|---|---|
| Place of installation | Wuhan |
| Remark | Good Performance |
| END USER | China University Of Geosciences,wuhan |
운영자 및 일정
Operator: Park, Jongwon
Date of setup: 23.11.24
Date of reporting: 23.11.24
Date of business trip : 17.12.27~17.12.29
개요
The DVIA-M1000 active vibration isolation platform is appropriately installed and functioning as intended.
Measurement date: 2023.11.24 (Friday)
Operator: DAEIL SYSTEMS Jongwon Park
Place of measurement: Wuhan
Equipment Model: Apreo
5.
M1000 내부 프로그램 성능 측정 결과
Z axis
X axis
Y axis
이 케이스 스터디 공유하기
케이스 스터디 정보
카테고리
설치 보고서
시리즈DVIA-M Series
작성일11-24-2023
태그
DVIA-M Series
Installation Report
China University Of Geosciences
Wuhan
Apreo
DVIA-M1000
230224R2
관련 케이스 스터디

DVIA-M Series
YIMO Shagang Zhangjiagang Thermo Fisher Apreo SEM DVIA-M1000 (240502R1) Installation Report
09-10-2024자세히

DVIA-M Series
Shagang Group Thermo Fisher Apreo DVIA-M1000 (230804R3) Set-up Report — Zhangjiagang
06-14-2024자세히

DVIA-M Series
Thermo Fisher Scientific Apreo 2S HiVac DVIA-M1000 Installation Report
11-09-2023자세히