설치 보고서
DVIA-ULF Series
07-27-2023
Fujian Zijin Liyuan Material Technology Sigma300 DVIA-U1000 (230620R3) Installation Report — Xiamen
DVIA-U Series
Installation Report
Fujian Zijin Liyuan
Sigma300
DVIA-U1000
230620R3
Xiamen
China
목차
Fujian Zijin Liyuan Material Technology Co., Ltd.
Fujian Zijin Liyuan Material Technology Co., Ltd.
(U1000_ 230620R3 Set up)
현장 확인 항목
| Target equipment | Sigma300 |
|---|---|
| Place of installation | Xiamen |
| Remark | Good Performance |
| END USER | Fujian Zijin Liyuan Material Technology Co., Ltd. |
운영자 및 일정
| Operator: Lee, Youngha Date of setup: 23.07.26 Date of reporting: 23.07.27 | Date of business trip : 17.12.27~17.12.29 |
|---|
개요
The DVIA-U1000 active vibration isolation platform is appropriately installed and functioning as intended. Measurement date: 2023.07.26 (Wednesday), Operator: DAEIL SYSTEMS, Youngha Lee Place of measurement: Xiamen, China Equipment Model: Sigma300
U1000 내부 프로그램 성능 측정 결과
Z축
X축
Y축
이 케이스 스터디 공유하기
케이스 스터디 정보
카테고리
설치 보고서
시리즈DVIA-ULF Series
작성일07-27-2023
태그
DVIA-U Series
Installation Report
Fujian Zijin Liyuan
Sigma300
DVIA-U1000
230620R3
Xiamen
China
관련 케이스 스터디

DVIA-ULF Series
Fujian Zijin Liyuan Material Technology Sigma300 DVIA-UB700 (230620R3) Installation Report
07-27-2023자세히

DVIA-ULF Series
Xi'an Polytechnic University Sigma300 DVIA-U1000 (220531R1) Installation Report
07-14-2023자세히

DVIA-ULF Series
DFDCHEM Guangxi Sigma300 DVIA-U1000 (220919R7) Installation Report — Guangxi
06-13-2023자세히